Avonlie Solar Farm
245 MW
Installed Capacity
450,000+
Duration Storage
100,000
Number of homes powered
Avonlie Solar Farm is a large-scale solar farm in Narrandera, NSW. The project comprises more than 450,000 solar panels with a total energy capacity of up to roughly 245 MW (DC).
The project received development approval from the Department of Planning & Environment in August 2019, and siteworks began in early Q4CY21, with initial energisation reached before the end of 2022.
Avonlie Solar Farm is directly connected to a dual 132 kV grid connection which passes through the project site about 20 km south of Narrandera.
Avonlie Solar Farm has the capability to generate approximately 500 GW hours of renewable energy per year, providing our growing customer base with a diversified supply of low cost clean energy.
Project Documents
- Avonlie Solar - EIS
- Avonlie Solar - Appendix A - SEARS
- Avonlie Solar - Appendix B - Layout and Design
- Avonlie Solar - Appendix C1 - Community Consultation Plan
- Avonlie Solar - Appendix C2 - Agency Consultation
- Avonlie Solar - Appendix D - Biodiversity Assessment
- Avonlie Solar - Appendix E - Aboriginal Cultural Herit
- Avonlie Solar - Appendix F - Visual Impact Assessment
- Avonlie Solar - Appendix G - Noise Assessment
- Avonlie Solar - Appendix H - Soil Survey Report
- Avonlie Solar - Appendix I - Flood Modelling
- Avonlie Solar - Appendix J - Traffic Access Assessment
- Avonlie Solar - Appendix K - Economic Impact Assessment
- View the Project Approval here
- Approval of Plan Strategy Accommodation and Employment Strategy
- Approval of Plan Strategy Biodiversity Management Plan
- Approval of Plan Strategy Environment Management Strategy or Study
- Approval of Plan Strategy Heritage Management Plan
- Approval of Plan Strategy or Study Stormwater Management Plan
- Approval of Plan Strategy Traffic Management Plan
- Biodiversity Management Plan
- Environmental Management Strategy
- Cultural Heritage Management Plan
- Stormwater Management Plan
- Accomodation and Employment Strategy
- Traffic Management Plan
- Approval of Plan Strategy Emergency Management Plan
- Emergency Management Plan
The Complaints register will be updated regularly and can be found here.